A project end to end
This page uses all eight members of the Lythos family, one after another, on an imaginary port expansion site. Every step was actually run with the program's own starter project (or a small change to it), and the output is quoted as it came.
About the numbers
Each step uses its own program's starter example; the soil profiles are not identical from step to step. The aim is not to finish one design but to show how the right tool answers the right question.
Office building footings — Lythos Bearing
A 2.5 × 4.0 m pad footing on layered ground (fill / stiff clay / dense sand); V = 1700 kN, H = 150 kN, M = 300 kNm.
lythos-bearing example -o office.bearing
lythos-bearing run office.bearingChecks
Bearing: FS = 2.96 ≥ 3.00 — NOT OK
Sliding: FS = 5.33 ≥ 1.50 — OK
Eccentricity: e/B = 0.071 ≤ 0.167 — OK
The bearing check is satisfied from B = 2.51 mVesić gives qult = 533.5 kPa; Meyerhof is the most conservative (466.0 kPa). Decision: B = 2.60 m. → Bearing examples
Preload fill for the warehouse yard — Lythos Settle
A 4 m high preload fill with a 12 m crest on soft clay:
values = forms.defaults()
values.update(shape="embankment", emb_crest=12.0, emb_height=4.0, emb_gamma=20.0)
r = Session(lang="en").analyse(values)s = 228.0 mm · t90 = 5.1 years · Settlement check: NOT OK
center total = 228.0 mm
shoulder total = 190.6 mm
midslope total = 108.5 mm
toe total = 17.0 mm90 % of the settlement takes 5.1 years — too long for a preload. Vertical drains will clearly be needed. → Settle examples
Stability of the fill — Lythos LE
A 6 m fill on the same kind of soft clay (su = 12 + 1.8·z kPa), raised in one lift:
one lift, 6 m, su0 = 12 kPa : FS = 0.896
stage 1, 3 m, su0 = 12 kPa : FS = 1.362
stage 2, 6 m, su0 = 24 kPa : FS = 1.366In one lift the fill fails (Bishop 0.896). Built in two stages, once consolidation under the first has raised su0 to 24 kPa, the second is safe at 1.37. Settle's t90 is the measure of that wait. → LE examples
Warehouse piled foundation — Lythos Pile
A 3 × 3 group of bored piles, D = 0.80 m, L = 20 m, Q = 10 000 kN:
CHECKS
Single pile: FS = 4.31 (required 2.50) — OK
Group: FS = 3.10 (required 2.50) — OK
Settlement: 32.8 mm (allowed 40.0 mm) — OK
Required length: L = 18.50 m (tip at 20.00 m)A length sweep shows an interesting detail: at L = 18 m the FS is only 1.84; as soon as the tip enters the dense sand (L = 20 m) it jumps to 4.31. Founding the piles in the dense sand is what matters. → Pile examples
Quay wall — Lythos SPWA
An 8 m retained height, an NZ 26 sheet pile quay with two rows of anchors; kh = 0.1:
Theoretical Required Embedment (D_req): 4.64 m
Design Embedment Depth (D_design): 6.00 m
...
Max. Absolute Moment: 564.58 kNm/m (LE: 559.61)
Max. Deflection: 73.3 mm (LE: 51.5)
STATUS: NOT OK - DEFLECTION EXCEEDED!Limit equilibrium says the wall is adequate; the staged beam-spring analysis shows the deflection exceeding the H/120 = 66.7 mm limit. That is exactly the value of putting the two side by side: a stiffer section or prestressed anchors are needed. → SPWA examples
Pumping station deep excavation — LythosFEA
An 8 m excavation behind a bored pile wall (D1000 @ 1.2 m) with two rows of prestressed anchors; six stages:
stage 5/6: 5 - stress anchor row 2, excavate to 22.0 m
stage 6/6: 6 - factor of safety
lowest factor of safety: 2.034Access ramp — Lythos MSEW
A 6 m MSE wall with 50×4 steel strips:
External stability (FS) value required
Sliding 2.99 1.50 OK
Overturning 6.02 2.00 OK
Bearing capacity 7.51 2.50 OK
Internal stability
Pullout 1.62 1.50 OK (z = 5.625 m)
Required uniform length: L = 5.13 m (FHWA minimum 4.20 m)Pullout of the top layer governs — that is where the overburden is smallest. → MSEW examples
Fill quarry — Lythos Kinematic
Six joint sets are screened against a 20 m rock face in the quarry:
Planar Sliding: 1 / 6
E3 CRITICALThe critical set goes to limit equilibrium: planar sliding with a tension crack, FS = 0.891. For FS = 1.5 the support required, at Hoek & Bray's optimum angle, is 697 kN/m. → Kinematic examples
Summary
| Structure | Tool | Result | Decision |
|---|---|---|---|
| Office footing | Bearing | FS = 2.96 < 3.00 | B = 2.60 m |
| Preload fill | Settle | 228 mm, t90 = 5.1 years | Vertical drains |
| Fill stability | LE | 0.90 → 1.36 / 1.37 | Two-stage construction |
| Warehouse piles | Pile | FS 4.31 / group 3.10 | L ≥ 18.5 m |
| Quay wall | SPWA | δ = 73 mm > 67 mm | Stiffer section |
| Deep excavation | FEA | SSR = 2.03 | Adequate |
| Access ramp | MSEW | Every check OK | L ≥ 5.13 m |
| Quarry face | Kinematic | FS = 0.89 | 697 kN/m of bolting |
Each step's project file comes from the example command and re-runs with run; every number on this page can be reproduced on your own machine.